Lab Problems 4 and 5
Lab Problem-4
Problem: Constructing a Product Launch Dependency Graph
Scenario:
You are part of a marketing team preparing for a new product launch. The launch involves several key activities, each with its own estimated duration and specific prerequisites. To ensure a smooth and timely launch, you need to model these activities as a Directed Acyclic Graph (DAG) to visualize the workflow and identify dependencies. This visual representation will be crucial for understanding the project's flow and later determining the critical path.
Your Goal:
Model the product launch activities as a Directed Acyclic Graph (DAG), representing each activity as a node and dependencies as directed edges. Clearly state the nodes (activities) and their durations, along with the edges (prerequisites).
Activity List:
A1: Market Research Analysis
Duration: 4 days
Prerequisites: None
A2: Product Feature Definition
Duration: 6 days
Prerequisites: A1
A3: Marketing Material Creation
Duration: 9 days
Prerequisites: A2
A4: Website Landing Page Development
Duration: 8 days
Prerequisites: A2
A5: Social Media Campaign Planning
Duration: 5 days
Prerequisites: A3
A6: PR Outreach & Press Release Drafting
Duration: 7 days
Prerequisites: A3
A7: Final Website Launch & Testing
Duration: 3 days
Prerequisites: A4, A5
A8: Post-Launch Performance Monitoring
Duration: 2 days
Prerequisites: A6, A7
Lab Problem-5
Problem: Calculating Earliest Start and Finish Times for a Research Project
Scenario:
You are managing a small research project for a university department. The project consists of several distinct phases, each with an estimated time commitment and dependencies on prior phases. To effectively plan and allocate resources, you need to perform a forward pass analysis to determine the earliest possible start and finish times for each research phase. This will help in setting realistic timelines and understanding the overall project schedule.
Your Goal:
For each phase in the research project, calculate its Earliest Start Time (ES) and Earliest Finish Time (EF). The ES for a phase is the earliest it can begin once all its prerequisites are completed. The EF for a phase is its ES plus its duration. Assume the project starts at day 0.
Phase List:
P1: Literature Review
Duration: 6 weeks
Prerequisites: None
P2: Experimental Design
Duration: 4 weeks
Prerequisites: P1
P3: Data Collection
Duration: 10 weeks
Prerequisites: P2
P4: Data Analysis
Duration: 8 weeks
Prerequisites: P3
P5: Manuscript Drafting
Duration: 12 weeks
Prerequisites: P4
P6: Peer Review Submission
Duration: 3 weeks
Prerequisites: P5
P7: Revisions and Finalization
Duration: 5 weeks
Prerequisites: P6
P8: Publication
Duration: 1 week
Prerequisites: P7
Comments
Post a Comment